Pool & Fitness Center

May 30, 2012
Black Bull Aquatic Director

Hillary Gallardo became part of the Black Bull team in May 2012 to supervise pool operations. Hillary is originally from San Diego and has been working as a lifeguard and Water Safety Instructor since the age of seventeen. In...

May 17, 2012

Big excitement out here today as we arrived to a full pool this morning! The water slowly started flowing at 9:00 A.M. yesterday. We watched with great anticipation thinking of summer poolside events. The kids' pool and hot tub are also filled; nearly ready...

November 10, 2011

The Black Bull Pool & Fitness Center construction continues apace! Black Bull Construction is on-scheduled to complete the Fitness Area & Locker Room in February 2012 and the Pool in early summer 2012.

November 4, 2011

The Pool & Fitness Center construction continues apace! The masonry work continues, the pool floor was poured, the stucco siding has begun, the windows are installed, the roofing continues and the electrical and plumbing work are in progress. 

Come by the Club to see the amazing...

October 26, 2011

The Pool & Fitness Center progress continues despite the chilly temperatures. The masonry work has started, as has the interior mechanical rough work. The hot tub area has been excavated and is ready for the pool contractor. The pool stairs have been installed, the pool seams are being...

October 14, 2011
pool and fitness center construction at Black Bull Golf Community in Bozeman, MT

In the 5 weeks since Black Bull Construction broke ground on the Pool & Fitness Center, the progress has been impressive. The walls are framed and the roof is 80% framed. The crews are working on the roof sheeting and the substructure for the pool is near completion. The stainless steel side...

September 29, 2011

The Pool & Fitness Center construction is in full swing and progress is swift thanks to the great weather and good crew. The foundations have been poured and treated, top plates installed, the back fill is in and the floor joists are being installed.

The next phase will be the framing...